# Connection Charging Rules

> The Connection Charging Rules carries 6 published figures read from 2 sources' own pages, from 20 to 2,843 GBP, read 7 November 2026.

Three Phase Cost · https://threephasecost.co.uk/datasets/connection-charging-rules/ · computed 2026-11-08

**Range of the published figures:** 20 to 2,843 GBP (range 20 to 2,843 GBP; 6 published figures; 4 of 9 sources read publish one).

4 of the 9 named sources read in full publish a figure; 5 publish none, read 7 November 2026.

## By rule

| Breakdown | Median | Range | Sources |
|---|---|---|---|
| rule NI standard housing charge | 2,843 GBP | 2,843 to 2,843 GBP | 1 |
| rule annual notice of rights | 12 month | 12 to 12 month | 1 |
| rule cost reallocation materiality threshold | 50 % | 50 to 50 % | 1 |
| rule unmetered connection works on adopted highway (35 working days) failure payment | 20 GBP | 20 to 20 GBP | 1 |
| rule CIC design submission decision within 10 working days failure payment (Demand LV) | 80 GBP | 80 to 80 GBP | 1 |
| rule CIC design submission decision within 10 working days failure payment (Demand HV) | 165 GBP | 165 to 165 GBP | 1 |
| rule CIC provide EHV point of connection within 30 working days failure payment | 80 GBP | 80 to 80 GBP | 1 |
| rule CIC design submission decision within 20 working days failure payment (EHV/132kV) | 245 GBP | 245 to 245 GBP | 1 |

## Every figure, with its source

One row per source: the figure the source's own page publishes, the page, and the day it was read.

| Source | Figure | Breakdown | Read |
|---|---|---|---|
| [Utility Regulator (NI) - NIE Networks revised Statement of Charges for Connection](https://www.uregni.gov.uk/news-centre/nie-networks-publishes-revised-statement-charges-connection-northern-irelands) | 2,843 GBP | NI standard housing charge | 2026-11-07 |
| [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance) | 245 GBP | CIC design submission decision within 20 working days failure payment (EHV/132kV) | 2026-11-07 |
| [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance) | 165 GBP | CIC design submission decision within 10 working days failure payment (Demand HV) | 2026-11-07 |
| [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance) | 80 GBP | CIC design submission decision within 10 working days failure payment (Demand LV) | 2026-11-07 |
| [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance) | 80 GBP | CIC provide EHV point of connection within 30 working days failure payment | 2026-11-07 |
| [Ofgem - DCUSA DCP407 Authority's decision](https://www.ofgem.gov.uk/sites/default/files/2023-03/DCUSA%20DCP407%20Authority%27s%20Decision1678198653685.pdf) | 50 % | cost reallocation materiality threshold | 2026-11-07 |
| [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance) | 20 GBP | unmetered connection works on adopted highway (35 working days) failure payment | 2026-11-07 |
| [The Electricity (Standards of Performance) Regulations 2015](https://www.legislation.gov.uk/uksi/2015/699/body/made) | 12 month | annual notice of rights | 2026-11-07 |

## The sentence each figure was read from (8)

- [Utility Regulator (NI) - NIE Networks revised Statement of Charges for Connection](https://www.uregni.gov.uk/news-centre/nie-networks-publishes-revised-statement-charges-connection-northern-irelands), read 2026-11-07: "This second approval reflects the final phase in implementing the increase in the Standard Housing Charge from £1,974 to £2,843, which is reflective of the remainder of NIE Network’s original ask, plus a true up to the current SoCC cost reflective calculation."
- [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance), read 2026-11-07: "CIC Generation EHV CIC Demand/Generation 132kV 65 £165 Design submission decision - within 20 working days £245"
- [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance), read 2026-11-07: "CIC Demand HV 20 £165 Design submission decision within 10 working days of request for approval £165 Complete final works - 20 working days Phased energisation works – 10 working days or later date as requested £245"
- [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance), read 2026-11-07: "CIC Demand LV 15 £80 Design submission decision within 10 working days of request for approval £80 Complete final works - 10 working days Phased energisation works - 5 working days or later date as requested £165"
- [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance), read 2026-11-07: "CIC Demand EHV 50 £245 Provide EHV POC within 30 working days £80 Inform the customer of planned date proposed to complete final works within 20 working days of ICP request £330"
- [Ofgem - DCUSA DCP407 Authority's decision](https://www.ofgem.gov.uk/sites/default/files/2023-03/DCUSA%20DCP407%20Authority%27s%20Decision1678198653685.pdf), read 2026-11-07: "paragraph 6 of Schedule 32 and include a materiality threshold, requiring that reallocation be triggered where there is a 50% increase or decrease in comparison to the"
- [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance), read 2026-11-07: "Unmetered Complete Works on Adopted Highway (35 working days) £20"
- [The Electricity (Standards of Performance) Regulations 2015](https://www.legislation.gov.uk/uksi/2015/699/body/made), read 2026-11-07: "(5) An electricity supplier must at least once in any period of 12 months dispatch to each of its domestic customers the information in any statement sent to it by an electricity distributor pursuant to paragraph (1)(b), provided that where in relation to any premises more than one person is a domestic customer, the obligation is satisfied by dispatching such information to any one of them."

## Read in full, publishes no figure

- [The Electricity (Connection Standards of Performance) Regulations 2015](https://www.legislation.gov.uk/uksi/2015/698/contents), read 2026-09-12: read in full and no accepted figure on the page
- [Ofgem - adjustments to the Guaranteed Standards of Performance 2026](https://www.ofgem.gov.uk/guidance/adjustments-guaranteed-standards-performance-2026), read 2026-10-17: read in full and no accepted figure on the page
- [Ofgem - UK Power Networks connection charging methodology and statement updates](https://www.ofgem.gov.uk/decision/uk-power-networks-connection-charging-methodology-and-statement-updates), read 2026-09-19: read in full and no accepted figure on the page
- [UK Power Networks connections library - the voltage rule](https://library.ukpowernetworks.co.uk/library/en/Connectionsquotations/worksinformation/4.13-The-Voltage-Rule/), read 2026-09-12: read in full and no accepted figure on the page
- [SSEN - Access SCR library](https://www.ssen.co.uk/about-ssen/library/access-scr/), read 2026-09-26: read in full and no accepted figure on the page

## Methodology

Every row is a verbatim sentence read from the named source's own page through our fetch service on the date shown, hash-pinned to the stored read (the sha of the page's visible text; the raw page is mirrored to R2). 4 of the 9 named sources that could be read published a usable figure; 5 published none and are recorded as not published, never filled in; 1 could not be read (blocked, dead or unreachable) and count nowhere. The headline figures (median, minimum, maximum, quartiles) are over ONE figure per source for each breakdown it prices, in GBP (a source's median where its page yielded several accepted sentences for one breakdown), so a page that gives figures for several breakdowns gives one for each and N counts 6 figures, never sentences; 9 candidate sentence(s) were refused by a reviewer with the reason recorded. The fuller derivation this dataset is chartered to grow into (not yet what the figures above are; they are each source's own published figure as read): one row per rule per jurisdiction (GB under Ofgem and the DCUSA charging methodologies, NI under the Utility Regulator's approved Statement of Charges), quoted verbatim with its effective date: the charging boundary after the Access SCR, the minimum-scheme rule that makes extra phases the customer's cost in full, the connection standards of performance and the working-day quotation deadlines with the payment for missing them, and the NI standard charge; the derivation is the CHANGE - what the buyer pays today against what the same job cost before 1 April 2023, and the count of rules that moved at each rate-year turn

## Sources

- [The Electricity (Connection Standards of Performance) Regulations 2015](https://www.legislation.gov.uk/uksi/2015/698/contents) (the publisher's own terms; quoted for reporting and comment)
- [The Electricity (Standards of Performance) Regulations 2015](https://www.legislation.gov.uk/uksi/2015/699/body/made) (the publisher's own terms; quoted for reporting and comment)
- [Ofgem - adjustments to the Guaranteed Standards of Performance 2026](https://www.ofgem.gov.uk/guidance/adjustments-guaranteed-standards-performance-2026) (the publisher's own terms; quoted for reporting and comment)
- [Ofgem - UK Power Networks connection charging methodology and statement updates](https://www.ofgem.gov.uk/decision/uk-power-networks-connection-charging-methodology-and-statement-updates) (the publisher's own terms; quoted for reporting and comment)
- [Utility Regulator (NI) - NIE Networks revised Statement of Charges for Connection](https://www.uregni.gov.uk/news-centre/nie-networks-publishes-revised-statement-charges-connection-northern-irelands) (the publisher's own terms; quoted for reporting and comment)
- [UK Power Networks connections library - the voltage rule](https://library.ukpowernetworks.co.uk/library/en/Connectionsquotations/worksinformation/4.13-The-Voltage-Rule/) (the publisher's own terms; quoted for reporting and comment)
- [SSEN - Access SCR library](https://www.ssen.co.uk/about-ssen/library/access-scr/) (the publisher's own terms; quoted for reporting and comment)
- [Energy Networks Association - DNO metered connections national outputs report](https://www.energynetworks.org/assets/images/Publications/2024/240404-dno-metered-connections-nor-april-2024-final.pdf) (the publisher's own terms; quoted for reporting and comment)
- [Ofgem - DCUSA DCP407 Authority's decision](https://www.ofgem.gov.uk/sites/default/files/2023-03/DCUSA%20DCP407%20Authority%27s%20Decision1678198653685.pdf) (the publisher's own terms; quoted for reporting and comment)
- [National Grid Electricity Distribution - connection guaranteed standards of performance](https://connections.nationalgrid.co.uk/connection-guaranteed-standards-of-performance) (the publisher's own terms; quoted for reporting and comment)

## Cite or embed

- The Connection Charging Rules carries 6 published figures read from 2 sources' own pages, from 20 to 2,843 GBP, read 7 November 2026.
- 4 of the 9 named sources read in full publish a figure; 5 publish none, read 7 November 2026.
- Connection Charging Rules, rule NI standard housing charge: median 2,843 GBP across 1 source, read 7 November 2026.
- Connection Charging Rules, rule annual notice of rights: median 12 month across 1 source, read 7 November 2026.
- Connection Charging Rules, rule cost reallocation materiality threshold: median 50 percent across 1 source, read 7 November 2026.
- Connection Charging Rules, rule unmetered connection works on adopted highway (35 working days) failure payment: median 20 GBP across 1 source, read 7 November 2026.
- Connection Charging Rules, rule CIC design submission decision within 10 working days failure payment (Demand LV): median 80 GBP across 1 source, read 7 November 2026.
- Connection Charging Rules, rule CIC design submission decision within 10 working days failure payment (Demand HV): median 165 GBP across 1 source, read 7 November 2026.
- Connection Charging Rules, rule CIC provide EHV point of connection within 30 working days failure payment: median 80 GBP across 1 source, read 7 November 2026.
- Connection Charging Rules, rule CIC design submission decision within 20 working days failure payment (EHV/132kV): median 245 GBP across 1 source, read 7 November 2026.

Cite as: "threephasecost.co.uk Connection Charging Rules", updated 2026-11-08, https://threephasecost.co.uk/datasets/connection-charging-rules/.

CSV: https://threephasecost.co.uk/datasets/connection-charging-rules.csv
JSON: https://threephasecost.co.uk/datasets/connection-charging-rules.json
Embed (plain HTML, static link back): see https://threephasecost.co.uk/datasets/connection-charging-rules/#median
